Dear Editor,
It was reported in the news media of Feb. 17 that due to bad contract management, the East Bank and East Coast Demerara Highway improvement projects funded by the Inter-American Development Bank (IDB) has cost the Govt. $543M and still counting for unfinished contract work on these road projects.
As a result of this large cost overrun and projects’ delay completion of nearly three years, the Govt. decided to terminate the contracts which were awarded to two contractors. For the records, these were contractors involved in construction of the Hope Canal, a Govt. funded project which had large time and cost overruns as well as several defects which surfaced after construction.
Minister of Public Infrastructure (MoPI) David Patterson appeared to have lapsed in the execution of his duties. It is inconceivable that he allowed these failed contractors as well as the supervising consultants, firstly to be awarded subsequent contracts despite their past poor performance on Govt. contracts and secondly, authorizing payments to them for work which was never done. In this respect, Minister Patterson should have reviewed the performance of his staff particularly the chief roads and bridge officer who failed to monitor the work of the supervisors and contractors and authorized partial payments to them for fictitious work done; hence the cause for the over-payment.
Minister Patterson is fully aware through his training and work experience that in any contract there are clauses whereby the supervising consultant monitoring construction of a project has to ensure that the work done was in accordance with the plans and specifications and partial payments are only recommended for work done and/or for materials on site. He is also expected to alert the Govt. of any contract delay and non-compliance with the plans and specifications.
Therefore it is unimaginable that the MoPI allowed the above- mentioned contractors to be over-paid and chalked-up large time overruns then allowed them to abandon the projects without any financial penalty while leaving the country with a heavy debt to service and unfinished projects to complete.
Emil McGarrel, Permanent Secretary, MoPI, implied in his statement that the IDB funded road projects did not allow the Govt. to impose penalties on contractors for non-performance of work, only termination could be enforced. The facts suggest otherwise since the IDB loan agreement with the Govt. did not have any restrictive clause regarding the imposition of penalties for non-performance by contractors.
Charles Sohan
GRA catch EXXON trying to hunch GUYANA over 11 BUS dollars in one shot!!!!
May 07, 2024
‘One Guyana’ Beach Football Championship Kaieteur Sports – Young Gunners males and Speightland ladies are Kings and Queens of the Sand One Guyana Beach Football Championship which concluded...Kaieteur News – The PPP/C’s congress was characterised by a glaring disconnect from the realities facing Guyana... more
By Sir Ronald Sanders Waterfalls Magazine – On April 10, the Permanent Council of the Organization of American States... more
Freedom of speech is our core value at Kaieteur News. If the letter/e-mail you sent was not published, and you believe that its contents were not libellous, let us know, please contact us by phone or email.
Feel free to send us your comments and/or criticisms.
Contact: 624-6456; 225-8452; 225-8458; 225-8463; 225-8465; 225-8473 or 225-8491.
Or by Email: [email protected] / [email protected]