Latest update November 2nd, 2024 1:00 AM
Sep 23, 2024 News
…contractor will utilise excess gas brought to shore by Exxon’s pipeline, sell 250MW to GPL
The Government of Guyana (GoG) through the Office of the Prime Minister on Sunday issued a Request For Proposals (RFP), seeking qualified companies to design, finance and operate Phase Two of the Gas-to-Energy (GTE) Project.
Phase One of the project includes a pipeline to transport the natural gas to shore as well as a Natural Gas Liquids facility and 300 megawatts (MW) power plant. According to the RFP, Phase Two of the GTE project seeks to utilize 75 million cubic feet of gas per day (MMCFD), piped to shore by ExxonMobil Guyana Limited (EMGL). It should be noted that Phase One only utilizes 50 million standard cubic feet per day (MMSCFD), which amounts to 40% capacity of Exxon’s 250 kilometer 12-inch pipeline. Phase Two will make use of the remaining 60% capacity of the pipeline connected to the Liza Fields in the Stabroek Block to Wales, West Bank Demerara.
The selected bidder will be tasked with the design, construction, and operation of a 250 MW combined-cycle power plant, to deliver 2,100 gigawatt hours (GWH) of electricity per annum. This will be sold to the Guyana Power and Light Inc (GPL) via a Power Purchase Agreement (PPA). It was made explicit that investors will recover their investment through the sale of electricity via a 20-to-25-year term (negotiable) Power Purchase Agreement (PPA) “at a price per Kilowatt Hour (KWH)” and via the monetization of the NGLs. At the end of the PPA term, the entire facility will revert to the GOG at no cost. “Phase II GTE will enjoy the same fiscal incentives as Phase I,” the RFP stated. In addition to the power plant, the contractor will design, construct and operate a NGL facility to produce approximately 6,000 barrels per day of NGL products (propane, butane, and C5+gasolene), utilizing 75 MMCFD of “rich gas.”
It was explained that the excess “lean gas,” estimated at 30 MMCFD will be transferred to the GoG at no cost, for utilisation in downstream industries, e.g. fertilizer production, to be located at Wales. The privately operated gas project will be located on no more than 100 acres of land, immediately adjacent to the existing 300 MW Integrated facility being developed by the GoG. “The project will be owned and financed 100% by the private sector, under a project finance structure, which will design and construct the integrated facilities, to a standard and specification that meets and or exceeds that of Phase I of the GTE,” the Office of the Prime Minister indicated.
It was also noted, “Only firms (consortia) adjudged to be experienced in Engineering Procurement and Construction (EPC) and Financing of comparable facilities, will be evaluated. The GOG shall have the right to approve the EPC contract and appoint an independent supervision firm, to ensure that the project is built per the EPC contract and acceptable quality and specifications, pre-approved by the GOG.” Bidders will be provided with the existing Employers’ Requirements for Phase I of the GTE project, along with a template of the EPC contract for reference.
In the meantime, government expects responses to the RFP to include financial projections of revenue, expenses, and investments returns using a number of variables including the PPA price per KWH, broken down into the following three elements “(a) payment for the gas; (b) operating and maintenance cost; (c) financing/amortization of the capital costs. Indicate the breakeven price and estimated sale price for each year along with an assumed inflation rate.”
Meanwhile, subject to ensuring sufficient revenue to operate the facility and recover the investment at an agreed rate of return, the GOG has reserved the right to: (i) buy-out the project (the Guyanese SPV), any-time after the construction and commissioning, at an agreed formula, such that the investor obtains a return of investment and reasonable accrued return based on the stated cost of capital; (ii) transfer of the entire volume of NGL’s to GOG/GPGI, who will market and distribute with Phase I NGL’s, either at zero cost or other agreed value. Responses to the RFP must be submitted by November 14, 2024. Notably, the GoG made it clear it “is not bound to accept any response to this RFP and reserves the right to select any Party for any specific element of the RFP and to annul the process at any time without further direction, without thereby incurring any liability to the affected interested parties.”
October 1st turn off your lights to bring about a change!
Nov 02, 2024
Kaieteur Sports- Today promises to be an exhilarating day of football action as the Petra-Courts Optical Pee Wee Under-11 School’s Football Tournament crowns its 2024 champions at the Ministry of...…Peeping Tom Kaieteur News- In every democracy worth its salt, the press serves as the watchdog, the thorn in the side... more
By Sir Ronald Sanders Kaieteur News – There is an alarming surge in gun-related violence, particularly among younger... more
Freedom of speech is our core value at Kaieteur News. If the letter/e-mail you sent was not published, and you believe that its contents were not libellous, let us know, please contact us by phone or email.
Feel free to send us your comments and/or criticisms.
Contact: 624-6456; 225-8452; 225-8458; 225-8463; 225-8465; 225-8473 or 225-8491.
Or by Email: [email protected] / [email protected]