As the $1.2B East Bank Berbice road project nears completion, 2.1 kilometres of the first layer of paved asphalt surface of the planned 5 kilometres has been completed.
Resident Engineer, Joel Tucker told the Department of Public Information that this covers the stretch of road from Everton to Edinburgh and the section in Islington. The remaining 2.9 kilometres will commence shortly.
Tucker said that despite challenges with the May/June rains, the exercise, which commenced in August 2017 will be completed by the end of the year.
“Presently, we’re 50 percent in terms of asphalt placed. It was difficult for us to place our sub-base during rainy weather, so now that the rains have eased up, we’ve begun most of our sub-base work in the Glasgow and Heathburn areas,” Tucker explained.
Some 1.9 kilometres of the base layer and the final layer of asphalt are slated for completion in Glasgow. Preparations are underway to begin the final layer of asphalt in the Edinburgh, Everton and Islington areas shortly.
Construction of the culvert at Baptiste Turn, Edinburgh, is finished, and another at Glasgow is approximately 90 percent complete. The remaining structures to be done are the bridges at Gay Park, Edinburgh, and recently-added Everton.
“We’re now driving piles for the bridge at the Everton location and that is scheduled to be completed at the end of November. It’s possible that we’ll complete the road works as scheduled, but we may not complete all the structures before the end of the year,” the Resident Engineer underlined.
The safety features such as guardrails and road signage will also be completed.
Meanwhile, the removal of utilities is almost completed with some minor Guyana Water Incorporated (GWI) utilities remaining.
Additionally, a total of 120 light-emitting diodes (LED) roadway lighting fixtures were installed between Stanleytown and Everton Village in August.
This multimillion-dollar venture is being executed by the Ministry of Public Infrastructure’s Special Project Unit, utilising its own equipment and employing residents from the East Bank Berbice area.
Dec 07, 2024
ExxonMobil Global Super League… Kaieteur Sports- Rangpur Riders dominated Cricket Victoria to win by 56 runs and become the inaugural ExxonMobil Guyana Global Super League (GSL) champions on a...…Peeping Tom Kaieteur News- Dennis Chabrol asked Bharrat Jagdeo a simple question and Jagdeo responded with acrobatics... more
By Sir Ronald Sanders Kaieteur News- The election of a new Secretary General of the Organization of American States (OAS),... more
Freedom of speech is our core value at Kaieteur News. If the letter/e-mail you sent was not published, and you believe that its contents were not libellous, let us know, please contact us by phone or email.
Feel free to send us your comments and/or criticisms.
Contact: 624-6456; 225-8452; 225-8458; 225-8463; 225-8465; 225-8473 or 225-8491.
Or by Email: [email protected] / [email protected]