Aug 16, 2016 News
The cries of the residents in the mining community of Mahdia, Region Eight, are being answered with the rehabilitation of the internal roads. However, Senior Hinterland Engineer, Ministry of Public Infrastructure, Naeem Mohamed, said that works are ongoing, despite challenges.
In an interview with the Government Information Agency (GINA), Mohamed said that the contractors are facing challenges with the removal of the Guyana Water Incorporated (GWI), Guyana Power and Light (GPL) and Guyana Telephone and Telegraph Company (GTT) utilities.
However, these are being addressed and the contractors are increasing the pace of work. To date, 15 percent of the work has been completed.
The approximately $720M allotted in the 2016 budget will see two kilometres of the roads concreted, along with several drains, Mohamed explained.
Additionally, works on the Mabura road will commence shortly. The contractors will be removing slush from the potholes and other areas, and in the dry season laterite material will be added, “so that the road will be more passable in time to come,” Mohamed explained.
The contracts were awarded to J. R. Ranch Incorporated, but due to the heavy rainfall works were delayed.
“It is challenging doing the grading, when the rains come. When you do a surface road in the rainy season it gets more complicated, the material becomes more plastic,” Mohamed said.
Mohamed pointed out to GINA that maintenance on the roads is usually executed annually, since it would not be economical to carry out periodic maintenance.
“We also cannot allow lots of time to pass before we do work on the road, so we have to choose the right time to get it done,” Mohamed said.
Early in 2016 when Minister of Natural Resources, Raphael Trotman and a team visited Mahdia, they were apprised of the poor state of roads in the community.
Trotman reportedly assured the residents at that time that works were slated to commence this year, since in the 2016 national budget funds were allocated for the paving of roads in Mahdia.
A total of $1.702B has been provided for rehabilitation of hinterland roads in Bartica, Mahdia, Ituni-Kwakwani and the Cassandra Crossing Bridge.
JAGDEO ADDING MORE DANGER TO GUYANA AND THE REGION
Apr 17, 2024
2024 CWI Regional 4-Day Championships Round 7…GHE vs. CCC Kaieteur Sports – After a highly-successful round 6, Guyana Harpy Eagles will look to take full advantage of the out-of-sorts...Kaieteur News – Every school teacher should take a close look at the students in his or her classroom. The probability... more
By Sir Ronald Sanders Waterfalls Magazine – On April 10, the Permanent Council of the Organization of American States... more
Freedom of speech is our core value at Kaieteur News. If the letter/e-mail you sent was not published, and you believe that its contents were not libellous, let us know, please contact us by phone or email.
Feel free to send us your comments and/or criticisms.
Contact: 624-6456; 225-8452; 225-8458; 225-8463; 225-8465; 225-8473 or 225-8491.
Or by Email: [email protected] / [email protected]