Apr 19, 2012 News
Under the Ministry of Public Works, three bids were submitted yesterday for the Amaila Falls road and transmission line clearing project (Section Seven) – Kuribrong River Bank to Amaila Falls Approach- at the National Procurement and Tender Administration Board (NPTAB).
Sithe Global, the developers of the Amaila Falls Hydropower Project, had chosen the China Railway First Group Company Limited to build the hydro plant in northwestern Guyana. This same contractor has also now placed a bid for a section of the road leading to Amaila Falls. This section involves virgin forest and is deemed the most challenging aspect of the road.
With an engineer’s estimate of $979,491,800 which was submitted by SRKN’gineering Consultants, the bids are as follows:
Bidder | Amount |
China Railway First Group Company Limited | $2,435,077,722.91 |
In a Joint venture – B&J Civil Works in collaboration with Ivor Allen Construction and Dynamic Engineering Company Ltd | $2,059,413,700 |
Hassan N. Pasha | $837,367,013 |
The Amaila Falls Hydropower project is being vigorously pursued by the administration on the basis that it would significantly reduce Guyana’s US$350M fuel import bill and minimise the impact of fuel price movement on the cost of generating power.
The project which has the capacity to provide over 140 megawatts of electricity is to be located along the Kuribrong River in Potaro, Region Eight.
The contract awarded to Makeshwar ‘Fip’ Motilall of Synergy Holdings Ltd was terminated by government in January after months of delays.
Since Motilall’s US$15.4M contract was terminated, for failure to honour one of the terms of a completion agreement, Toolsie Persaud Quarries Inc. was awarded the contract to build the Kurupukari junction and it also holds the contract for section four. The project, which will now be executed in lots, will see other contractors being recruited.
Section five has been allocated to Ivor Allen, while section six is yet to be allocated.
Meanwhile, under the Guyana Revenue Authority (GRA), the NPTAB received six bids for the completion and modification of the CLICO building, Camp Street, Georgetown.
The engineer’s estimate is $253,997,117 and the bids:
Bidder | Amount |
G. Bovell Construction Services | $213,004,132 |
Andrew Howard Construction Services | $220,599,302 |
Pacific Service System | $424,849,865 |
Cummings Contracting & Construction Services | $180,179,297 |
Aura Engineering Company | $215,112,370 |
Cummings Electrical Company Ltd | $227,157,135 |
Where is the BETTER MANAGEMENT/RENEGOTIATION OF THE OIL CONTRACTS you promised Jagdeo?
Apr 20, 2024
– Elton Dharry and Dexter Marques to headline tonight’s card Kaieteur Sports – The Everest Cricket Club pavilion crackled with tension yesterday as the Guyana Boxing Board hosted its...Kaieteur News – Once a habit has been drilled into you, it returns almost automatically when you return to the setting... more
By Sir Ronald Sanders Waterfalls Magazine – On April 10, the Permanent Council of the Organization of American States... more
Freedom of speech is our core value at Kaieteur News. If the letter/e-mail you sent was not published, and you believe that its contents were not libellous, let us know, please contact us by phone or email.
Feel free to send us your comments and/or criticisms.
Contact: 624-6456; 225-8452; 225-8458; 225-8463; 225-8465; 225-8473 or 225-8491.
Or by Email: [email protected] / [email protected]